NEWS





 




Newsletter -
Volume 1 Issue 3

MANAGEMENT OF CHANGE AND COMPLIANCE

A company wanted to modify a chemical process at one of its older facilities to make it more productive and competitive with newer technology currently used in the industry. Project planning and obtaining budget approvals was assigned to the production department. Subsequently, all the necessary construction contracts were issued, new equipment purchased, and scheduling finalized. Work began on a weekend in mid-January and was halted that Monday. Why?

Upon arrival at the facility on Monday morning, the EHS manager saw the work in progress and was surprised to see the installation of new equipment. The production department had never submitted the project plan to EHS for review. The Production Manager explained that the work was only a modification to the current process and he did not realize that the work may be subject to any regulatory requirements. The EHS Manager had no choice but to request that further work be suspended until a complete and thorough review of procedural and equipment changes was completed. Upon review of the plan the EHS Manager found that the process modification resulted in the following:

• Increase in process throughput
• Increase in air emissions
• Increase in pollutant loading to the facility’s waste water treatment system

In addition, the modified process would also require retraining of the current operators prior to start-up. Unfortunately, several of the above items required the facility to obtain appropriate environmental permits prior to initiation of the project. The work was suspended at considerable inconvenience, potential economic loss, and additional Agency scrutiny.

The company did not have a written “management of change (MOC)” program which would have provided the necessary management procedures and sign-offs required when procedural or equipment changes are contemplated. An effective MOC program prevents events such as the above from occurring. Although, the illustration above describes an environmental permitting situation, most MOC events are not as obvious. They comprise more routine activities that may impact the health and safety of employees including such “minor issues” as personnel changes in key positions and changing the set points of safety equipment (i.e., pressure relief valves).

The objective of a Management of Change (MOC) program is to ensure all process changes are properly identified, analyzed and controlled prior to starting or resuming operation. Note that an MOC program is specifically required under the OSHA Process Safety Management (PSM) standard 29 CFR 1910.119 (l)(1) and the EPA Chemical Accident Prevention Provisions (also known as RMP) under 40 CFR 68.75. However, every company, whether required by the regulations or not, would greatly benefit by establishing a written program for managing operational changes. A properly written and managed MOC program prevents accidents and reduces liability.

Click here to contact a CTI associate to learn more about the above topics . . . .

 


"YOUR COMPLIANCE IS OUR GOAL"

About Us    The Compliance Team    Services    News/Resources    Contact Us    Home
Copyright © 2005 CTI - All Rights Reserved